Step | Action | Value | Yes | No |
---|---|---|---|---|
1 |
Is the voltage reading within the specification? | Battery voltage | ||
2 | Connect a voltmeter from the BAT terminal at the generator and to ground. Is the voltage reading within the specification? | Battery voltage | ||
3 |
Is the voltage reading within the specifications? | 13-16 V | ||
4 | Perform a generator bench check. Refer to Generator Assembly Bench Check. Is the voltage reading within the specifications? | 13-16 V | ||
5 | Backprobe the BRN 25 wire at the I/P cluster connector with a voltmeter J 39200 to ground. Is the voltage reading within the specification? | Battery voltage | ||
6 | Backprobe the PNK 39 wire at the I/P cluster connector terminal 28 with a voltmeter J 39200 to ground. Is the voltage reading within the specification? | Battery voltage | ||
7 | Locate and repair an open in PNK 39 wire from the I/P fuse block to the I/P cluster. Has the repair been completed? | -- | System OK | -- |
8 | Repair RED 2 wire from the S106 to the generator. Has the repair been completed? | -- | System OK | -- |
9 | Perform a battery load test. Refer to Battery Load Test . Is the battery serviceable? | -- | ||
10 | Install a replacement generator. Refer to Generator Replacement in Engine Mechanical. Has the repair been completed? | -- | System OK | -- |
11 | Locate, repair open in BRN 25 wire from the I/P cluster to the generator. Has the repair been completed? | -- | System OK | -- |
12 |
Has the repair been completed? | -- | System OK | -- |
13 | Install a battery. Refer to Battery Replacement . Has the repair been completed? | -- | System OK | -- |
14 | Charge the battery. Refer to Battery Charging. Has the repair been completed? | -- | System OK | -- |