Step | Action | Value(s) | Yes | No | ||||
---|---|---|---|---|---|---|---|---|
1 |
Refer to Using Fused Jumper Wires in Wiring Systems. Did the fuel gauge move toward EMPTY? | -- | Go to Step 2 | Go to Step 5 | ||||
2 | Inspect CKT 150 (BLK) for an open condition between the fuel level sensor connector, cavity D and G300 (P32), or G400 (P42). Did you find a condition? | -- | Go to Step 3 | Go to Step 4 | ||||
3 | Repair the open in CKT 150 (BLK) between the fuel level sensor connector and G300 (P32), or G400 (P42). Did you complete the repair? | -- | System OK | -- | ||||
4 | Replace the fuel level sensor. Refer to one of the following procedures in Engine Controls:
Did you complete the repair? | -- | System OK | -- | ||||
5 |
Refer to Using Connector Test Adapters in Wiring Systems. Did the fuel gauge move toward EMPTY? | -- | Go to Step 6 | Go to Step 7 | ||||
6 | Repair the open in CKT 30 (PPL) between the instrument cluster connector and the fuel level sensor connector. Did you complete the repair? | -- | System OK | -- | ||||
7 | Replace the instrument cluster. Did you complete the repair? | -- | System OK | -- |
Step | Action | Value(s) | Yes | No | ||||||
---|---|---|---|---|---|---|---|---|---|---|
1 |
Did the voltage measure less than the specified value? | 10.0 V | Go to Step 2 | Go to Step 3 | ||||||
2 | Locate and repair the open or short to ground in CKT 30 (PPL) between the VCM and the instrument cluster connector, cavity 16. Did you complete the repair? | -- | System OK | -- | ||||||
3 |
Does the FUEL gauge continue to indicate FULL? | -- | Go to Step 4 | Go to Step 6 | ||||||
4 |
Did the resistance measure greater than the specified value? | 1.0 ohms | Go to Step 5 | Go to Step 10 | ||||||
5 | Locate and repair the open in CKT 30 (PPL) between the instrument cluster connector and the VCM connector C1. Did you complete the repair? | -- | System OK | -- | ||||||
6 |
Did the resistance measure within the specified values? | 40 ohms-250 ohms | Go to Step 7 | Go to Step 8 | ||||||
7 | Replace the VCM. Refer to one of the following procedures in Engine Controls:
Did you complete the repair? | -- | System OK | -- | ||||||
8 |
Did the measure resistance within the specified values? | 40 ohms-250 ohms | Go to Step 9 | Go to Step 11 | ||||||
9 | Locate and repair the open in CKT 1589 (PPL) or CKT 470 (BLK) between the fuel pump module and the VCM. Did you complete the repair? | -- | System OK | -- | ||||||
10 | Replace the instrument cluster. Did you complete the repair? | -- | System OK | -- | ||||||
11 | Replace the fuel pump module. Refer to one of the following procedures in Engine Controls: Did you complete the repair? | -- | System OK | -- |