GM Service Manual Online
For 1990-2009 cars only

Diagnostic Instructions

    • Perform the Diagnostic System Check - Vehicle prior to using this diagnostic procedure.
    • Review Strategy Based Diagnosis for an overview of the diagnostic approach.
    •  Diagnostic Procedure Instructions provide an overview of each diagnostic category.

DTC Descriptors

DTC P0412 : Secondary Air Injection (AIR) Solenoid Control Circuit

DTC P0418 : Secondary Air Injection (AIR) Pump Control Circuit

Diagnostic Fault Information

Circuit

Short to Ground

Open/High Resistance

Short to Voltage

Signal Performance

Solenoid Relay Coil Supply

P0412

P0411, P0412

P0690

--

Solenoid Relay Control

P0412

P0411, P0412

P0411, P0412, P0690

--

Solenoid Relay Switch Supply

P0411

P0411

--

--

Pump Relay Coil Supply

P0102, P0412, P0418,

P0418

P0690, P0418

--

Pump Relay Control

P0418

P0418

P0411, P0418, P0690, P2431

--

Pump Relay Switch Supply

P0411

P0411

--

--

Circuit/System Description

The secondary air injection (AIR) system aids in the reduction of hydrocarbon emissions during a cold start. The system forces fresh filtered air into the exhaust stream in order to accelerate the catalyst operation. The secondary AIR injection pump, provides filtered air on demand to the AIR check valve assembly. The AIR check valve assembly controls the flow of air from the AIR pump to the exhaust manifold. The AIR CNTRL relay supplies the current needed to operate the AIR solenoid that is integral to the check valve assembly. A pressure sensor, also integral to the check valve assembly, is used to monitor the air flow from the AIR pump. The control module supplies the internal pressure sensor with a 5-volt reference, an electrical ground, and a signal circuit. The signal circuit provides the control module with a voltage relative to internal AIR pressure changes.

The AIR diagnostic uses 3 phases to test the AIR system:

    • DTCs P0411 and P2430 run during Phase 1
    • DTCs P2430 and P2440 run during Phase 2
    • DTC P2444 runs during Phase 3

In all 3 phases, testing is accomplished by comparing the measured pressure against the expected pressure. The control module can detect faults in the AIR pump, AIR solenoid, pressure sensor , and the exhaust check valve. The pressure sensor can also detect leaks and restrictions in the secondary AIR system plumbing.

Conditions for Running the DTC

    • The system voltage is between 9-18 volts.
    • This DTC runs on a 250 ms loop.
    • DTC P0412 and DTC P0418 run continuously when the above conditions are met.

Conditions for Setting the DTC

    • The actual and expected states of the AIR solenoid and AIR pump relay control circuits do not match.
    • The condition exists for at least 5 seconds.

Action Taken When the DTC Sets

DTCs P0412 and P0418 are Type B DTCs.

Conditions for Clearing the MIL/DTC

DTCs P0412 and P0418 are Type B DTCs.

Reference Information

Schematic Reference

Engine Controls Schematics

Connector End View Reference

    •  Electrical Center Identification Views
    •  Engine Controls Connector End Views
    •  Engine Control Module Connector End Views

Electrical Information Reference

    •  Circuit Testing
    •  Connector Repairs
    •  Testing for Intermittent Conditions and Poor Connections
    •  Wiring Repairs

Description and Operation Reference

Secondary Air Injection System Description

DTC Type Reference

Powertrain Diagnostic Trouble Code (DTC) Type Definitions

Scan Tool Reference

    •  Scan Tool Data List
    •  Scan Tool Data Definitions
    •  Scan Tool Output Controls

Circuit/System Verification

  1. Ignition ON, command the affected relay ON and OFF with a scan tool. Feel or listen to verify that the affected relay turns ON and OFF with each command.
  2. Engine running, observe the DTC information with a scan tool. DTCs P0412 or P0418 should not set.
  3. Operate the vehicle within the Conditions for Running the DTC. You may also operate the vehicle within the conditions that you observed from the Freeze Frame/Failure Records data.

Circuit/System Testing

  1. Ignition OFF, disconnect the affected relay.
  2. Ignition ON, connect a test lamp between the positive terminal at the battery and the relay control circuit terminal.
  3. Command the relay ON and OFF with a scan tool. The test lamp should turn ON and OFF when changing between the commanded states.
  4. If the test lamp is always ON, test the relay control circuit for a short to ground. If the circuit tests normal, replace the ECM.
    If the test lamp is always OFF, test the relay control circuit for a short to voltage or an open/high resistance. If the circuit tests normal, replace the ECM.
  5. Connect an appropriately fused jumper wire between the positive voltage terminal at the battery and the load voltage supply circuit terminal and verify load activation.
  6. If the load does not activate, test the load voltage supply circuit for a short to ground or an open/high resistance. If the circuit tests normal, replace the load.
  7. Ignition ON, connect an appropriately fused jumper wire between the relay switch voltage supply circuit terminal and the load voltage supply circuit terminal and verify load activation.
  8. If the load does not activate, test the relay switch voltage supply circuit for a short to ground or an open/high resistance. If the circuit tests normal and its fuse is open, test all components connected to the fuse and replace as necessary.
  9. Ignition ON, verify that a test lamp illuminates between the relay coil voltage supply circuit terminal and ground.
  10. If the test lamp does not illuminate, test the relay coil voltage supply circuit for a short to ground or an open/high resistance.
  11. If all circuits and the ECM test normal, test or replace the affected relay.

Component Testing

Relay Test

  1. Test between the normally-closed switch terminals, if any, for 0 ohms.
  2. Test between the normally-open switch terminals for infinite ohms.
  3. Test between each switch terminal and either coil terminal for infinite ohms.
  4. Connect the relay coil terminals to ground and fused power to energize the relay.
  5. Test between the normally-closed switch terminals, if any, for infinite ohms.
  6. Test between the normally-open switch terminals for 0 ohms.
  7. Test between each switch terminal and either coil terminal for 0 volts.

Repair Verification

Ignition ON, command the relay ON and OFF with a scan tool. Feel or listen to verify that the relay turns ON and OFF with each command.