Removal Procedure

Caution: Refer to Approved Equipment for Collision Repair Caution in the Preface section.

  1. Disable the SIR system. Refer to SIR Disabling and Enabling .
  2. Disconnect the negative battery cable. Refer to Battery Negative Cable Disconnection and Connection .
  3. Remove all related panels and components.
  4. Remove the front impact bar. Refer to Front Bumper Impact Bar Replacement .
  5. Note the location and remove the sealers and anti-corrosion materials from the repair area. Refer to Anti-Corrosion Treatment and Repair .
  6. Restore as much of the damage as possible to the factory specifications. Refer to Dimensions - Body .
  7. Caution: Refer to Collision Sectioning Caution in the Preface section.


    Object Number: 1214888  Size: SH
  8. Determine the sectioning joint location from the center of the rear upper radiator support bolt (1)

  9. Object Number: 1198416  Size: SH
  10. Measure 67 mm (2 5/8 in) (a) forward from the center of the rear upper radiator support bolt.

  11. Object Number: 1198420  Size: SH
  12. Mark the top of the frame rail at the sectioning location.
  13. At the mark align a sliding square or similar tool (1) square to surface to the vertical walls of the frame rail.
  14. Scribe a line to both sides of the frame rail.

  15. Object Number: 1198423  Size: SH
  16. Apply masking tape (1) to the scribe line completely around the frame rail.

  17. Object Number: 1198424  Size: SH
  18. Cut the frame rail at the rear edge of the tape line using a reciprocating saw or equivalent tool (1).

  19. Object Number: 1198425  Size: SH
  20. Remove the damaged frame rail end section (1).

Installation Procedure


    Object Number: 748652  Size: SH
  1. Grind the existing frame rail seam to taper the seam at a 45-degree angle.
  2. Clean and prepare all of the welded mating surfaces.
  3. Apply 3M weld-thru coating P/N 05916 or equivalent as necessary to all bare metal surfaces.

  4. Object Number: 1198427  Size: SH
  5. Position the service frame section (1) to the existing frame.

  6. Object Number: 1198429  Size: SH
  7. Maintain a gap of one and one half frame rail metal thickness at the sectioning joint (1) and clamp in place.
  8. Inspect the frame measurements three-dimensional to ensure proper position of the service frame.

  9. Object Number: 1198433  Size: SH
  10. Using a Metal Inert Gas (MIG) welder (1), continuous-weld the upper and lower horizontal joints from corner to corner.
  11. Using a MIG welder, continuous-weld the upper and lower vertical joints from corner to corner.
  12. Install the front impact bar. Refer to Front Bumper Impact Bar Replacement .
  13. Apply the sealers and anti-corrosion materials to the repair area. Refer to Anti-Corrosion Treatment and Repair .
  14. Important: DO NOT top coat any bonding surface. Use primer only on bonding surfaces. Refer to adhesive manufacturer's recommendations.

  15. Paint the repair area. Refer to Basecoat/Clearcoat Paint Systems .
  16. Install all related panels and components.
  17. Connect the negative battery cable. Refer to Battery Negative Cable Disconnection and Connection .
  18. Enable the SIR system. Refer to SIR Disabling and Enabling .