11.1. | Slide the boot (1) back along the cable. |
11.2. | Remove the battery positive/starter cable nut (2). |
11.3. | Remove the battery positive/starter cable terminal (3) from the stud (4). |
Caution: Refer to Fastener Caution in the Preface section.
2.1. | Install the cable terminal (3) on the generator stud (4). The wire should be between the 2 and 4 o'clock position. |
2.2. | Install the terminal nut (2) and tighten to 20 N·m (15 lb ft). |
2.3. | Slide the boot (1) back into place over the stud (4) and the nut (2). |
Note: Ensure the engine harness leads are positioned on the solenoid prior to the positive cable terminal being installed.
• | Tighten the large nut (2) to 12 N·m (106 lb in). |
• | Tighten the small nut to 4 N·m (35 lb in). |
11.1. | Slide the boot (1) back along the cable. |
11.2. | Remove the battery positive/starter cable nut (2). |
11.3. | Remove the battery positive/starter cable terminal (3) from the stud (4). |
Caution: Refer to Fastener Caution in the Preface section.
2.1. | Install the cable terminal (3) on the generator stud (4). The wire should be between the 2 and 4 o'clock position. |
2.2. | Install the terminal nut (2) and tighten to 20 N·m (15 lb ft). |
2.3. | Slide the boot (1) back into place over the stud (4) and the nut (2). |
Note: Ensure the engine harness leads (2) are positioned on the solenoid prior to the positive cable terminal being installed.
• | Tighten the large nut (2) to 12 N·m (106 lb in). |
• | Tighten the small nut to 4 N·m (35 lb in). |
Tighten
Tighten the battery positive cable routing clip bolt to 35 N·m (26 lb ft).