- Install the J 21366
to the transmission bell housing to retain the torque converter.
- Raise the transmission into place and remove the J 21366
from the transmission.
- Slide the transmission straight onto the locating pins while lining up the marks on the flywheel and the torque converter made during removal.
The torque converter must be flush onto the flywheel and rotate freely by hand.
Notice: Use the correct fastener in the correct location. Replacement fasteners
must be the correct part number for that application. Fasteners requiring
replacement or fasteners requiring the use of thread locking compound or sealant
are identified in the service procedure. Do not use paints, lubricants, or
corrosion inhibitors on fasteners or fastener joint surfaces unless specified.
These coatings affect fastener torque and joint clamping force and may damage
the fastener. Use the correct tightening sequence and specifications when
installing fasteners in order to avoid damage to parts and systems.
- Install the studs and the bolt securing the transmission to the engine.
Tighten
Tighten the studs and the bolt to 50 N·m (37 lb ft).
- Install the transmission oil cooler lines to the transmission.
- Install the flywheel to torque converter bolts.
Tighten
Tighten the flywheel to torque converter bolts to 63 N·m (46 lb ft).
- Install the torque converter access plug.
- Install the fuel line bracket bolt to the left side of the transmission.
Tighten
Tighten the fuel line bracket bolt to 35 N·m (25 lb ft).
- Connect the following to the transmission:
• | The main electrical connector. |
• | The Park/Neutral Position switch connector. |
• | The transmission vent hose. |
- Install the heat shield to the transmission.
- Install the heat shield bolts.
Tighten
Tighten the heat shield bolts to 17 N·m (13 lb ft).
- Install the shift cable end to the transmission shift lever ball stud.
- Install the transfer case, if equipped. Refer to
Transfer Case Assembly Replacement
in Transfer Case.
- Connect the vent tube hose and the electrical connections to the transfer case, if equipped.
- If equipped with a transfer case, install the front propeller shaft. Refer to
Front Propeller Shaft Replacement
in Propeller Shaft.
- Install the exhaust crossover pipe assembly. Refer to
Exhaust Manifold Pipe Replacement
in Engine Exhaust.
- Install the transmission mount.
- Install the transmission mount bolts.
Tighten
Tighten the transmission mount bolts 25 N·m (18 lb ft).
- Raise the transmission.
- Install the transmission support to the vehicle.
- Install the nuts and bolts securing the transmission support to the frame.
Tighten
Tighten the bolts and nuts to 46 N·m (35 lb ft).
- Lower the transmission to the support frame.
- Install the transmission mount nuts.
Tighten
Tighten the transmission mount nuts to 46 N·m (35 lb ft).
- Remove the transmission jack from the transmission.
- Install the rear propeller shaft. Refer to
Rear Propeller Shaft Replacement
in Propeller Shaft.
- Lower the vehicle.
- Connect the negative battery cable. Refer to
Battery Negative Cable Disconnection and Connection
in Engine Electrical.
- Fill the transmission with approved transmission fluid. Refer to
Automatic Transmission Fluid and Filter Replacement
.