Step | Action | Values | Yes | No |
---|---|---|---|---|
Schematic Reference: Instrument Cluster Schematics | ||||
1 | Did you perform the IPC Diagnostic System Check? | -- | Go to Step 2 | |
2 | Turn on the ignition. Does the volt gage display approximately battery voltage? | -- | Go to Testing for Intermittent Conditions and Poor Connections in Wiring Systems | Go to Step 3 |
3 |
Does the Ignition 1 parameter measure within the specified values? | 9-16 V | Go to Step 6 | Go to Step 4 |
4 | Test the ignition 1 voltage circuit for an open. Refer to Circuit Testing and to Wiring Repairs in Wiring Systems. Did you find and correct the condition? | -- | Go to Step 7 | Go to Step 5 |
5 | Inspect for poor connections at the harness connector of the IPC. Refer to Testing for Intermittent Conditions and Poor Connections and to Connector Repairs in Wiring Systems. Did you find and correct the condition? | -- | Go to Step 7 | Go to Step 6 |
6 |
Important: Program the replacement IPC. Replace the IPC. Refer to Instrument Cluster Replacement . Did you complete the replacement? | -- | Go to Step 7 | -- |
7 | Operate the system in order to verify the repair. Did you correct the condition? | -- | System OK | Go to Step 2 |