Notice: Refer to Fastener Notice in the Preface section.
- Inspect the EVAP canister purge solenoid valve seal for damage, replace as necessary.
- Install the EVAP canister purge solenoid valve (3) and bolt (2).
Tighten
Tighten the bolt to 16 N·m (12 lb ft).
- Inspect the MAP sensor seal for damage, replace as necessary.
- Install the MAP sensor and bracket.
- Inspect the throttle body seal for damage, replace as necessary.
- Apply threadlock to the throttle body bolts/studs threads. Refer to
Adhesives, Fluids, Lubricants, and Sealers
for the correct part number.
- Install the throttle body and bolts/studs.
Tighten
Tighten the bolts/studs to 10 N·m (89 lb in).
- Install the inlet manifold tuning valve, and bolts.
Tighten
Tighten the bolts to 10 N·m (89 lb in).
- Install the NEW upper to lower intake manifold gaskets.
- Set the upper intake manifold onto the lower intake manifold.
- Apply threadlock to the upper intake manifold bolts/stud threads. Refer to
Adhesives, Fluids, Lubricants, and Sealers
for the correct part number.
- Install the upper intake manifold bolts (1, 2) and stud (3).
Tighten
Tighten the bolts and stud to 25 N·m (18 lb ft).
- Install the generator rear brace.
- Install the generator ball stud.
Tighten
Tighten the bolt to 20 N·m (15 lb ft).
- Install the generator upper bolt.
Tighten
Tighten the bolt to 50 N·m (37 lb ft).
- Install the 2 ignition coil bolts (1).
Tighten
Tighten the bolts to 25 N·m (18 lb ft).
- Install the inlet and outlet pipe (2, 3) to the studs.
- Install the heater inlet and outlet pipe nuts (1) to the throttle body studs.
Tighten
Tighten the nuts to 10 N·m (89 lb in).
- Install the left side spark plug wires.
- Connect the left side spark plug wires to the spark plugs.
- Connect the left side spark plug wires to the ignition coil.
- Engage the spark plug wire retainer clips to the intake manifold bracket and the heater inlet/outlet pipe.
- Install the air cleaner outlet duct. Refer to
Air Cleaner Outlet Duct Replacement
.
- Connect the inlet manifold valve electrical connector (1).
- Connect the EVAP canister purge solenoid electrical connector (1).
- Connect the ETC electrical connector (2).
- Connect the MAP sensor electrical connector (1).
- Install the radiator surge tank inlet pipe.
- Install the radiator surge tank inlet pipe bolts.
Tighten
Tighten the bolts to 10 N·m (89 lb in).
- Install the radiator surge tank inlet hose to the inlet pipe.
- Position the radiator surge tank inlet hose clamp.
- Install the brake booster vacuum hose (1) to the intake manifold.
- Position the vacuum hose clamp at the intake manifold.
- Install the PCV foul air tube. Refer to
Plastic Collar Quick Connect Fitting Service
.
- Install the PCV fresh air tube. Refer to
Plastic Collar Quick Connect Fitting Service
.
- Install the fuel and EVAP pipes to the retainer clip (2) and close the clip.
- Connect the fuel feed pipe (3) quick connect fitting to the fuel rail. Refer to
Metal Collar Quick Connect Fitting Service
.
- Connect the EVAP emission pipe (1) to the purge solenoid. Refer to
Plastic Collar Quick Connect Fitting Service
.
- Fill the cooling system. Refer to
Cooling System Draining and Filling
.
- Install the intake manifold cover. Refer to
Intake Manifold Cover Replacement
.
- Connect the negative battery cable. Refer to
Battery Negative Cable Disconnection and Connection
.