Notice: Refer to Fastener Notice in the Preface section.
Tighten
Tighten the generator positive cable nut to 9 N·m (80 lb in).
Tighten
Tighten the generator bolts to 50 N·m (37 lb ft).
Tighten
Tighten the bolts to 50 N·m (37 lb ft).
Tighten
Tighten the A/C line bracket bolt to 10 N·m (89 lb in).
4.1. | Slide the boot (1) down revealing the terminal stud. |
4.2. | Remove the generator cable nut (2) from the terminal stud. |
4.3. | Remove the generator cable (3). |
Notice: Use the correct fastener in the correct location. Replacement fasteners must be the correct part number for that application. Fasteners requiring replacement or fasteners requiring the use of thread locking compound or sealant are identified in the service procedure. Do not use paints, lubricants, or corrosion inhibitors on fasteners or fastener joint surfaces unless specified. These coatings affect fastener torque and joint clamping force and may damage the fastener. Use the correct tightening sequence and specifications when installing fasteners in order to avoid damage to parts and systems.
Tighten
Tighten the bolts to 50 N·m (37 lb ft).
3.1. | Install the generator cable (3). |
3.2. | Install the generator cable nut (2) to the terminal stud. |
Tighten
Tighten the nut to 9 N·m (80 lb in).
3.3. | Slide the boot (1) over the terminal stud. |