Step | Action | Value(s) | Yes | No |
---|---|---|---|---|
1 | Did you perform the Data Link Communications Systems Check? | -- | Go to Step 2 | |
2 |
Can communications be established? | -- | System OK | Go to Step 3 |
3 |
Is the resistance greater than the specified value? | 10M ohms | Go to Step 5 | Go to Step 4 |
4 | Locate and repair the short to ground in CKT 1807 (PPL). Did you complete the repair? | -- | System OK | -- |
5 | Use a J 39200 DMM in order to measure the voltage on the DLC from terminal 2 to terminal 5. Is the voltage greater than the specified value? | 1.0 V | Go to Step 6 | Go to Step 7 |
6 | Locate and repair the short to B+ in CKT 1807 (PPL). Did you complete the repair? | -- | System OK | -- |
7 | Use a J 39200 DMM in order to measure the resistance from the DLC terminal 2 to the PCM connector C3, cavity C8, or to the VCM connector C4, cavity 11. Is the resistance greater than the specified value? | 1.0 ohms | Go to Step 8 | Go to Step 9 |
8 | Locate and repair the open in CKT 1807 (PPL). Did you complete the repair? | -- | System OK | -- |
9 |
Can communications be established? | -- | System OK | Go to Step 1 |