FLUID LEAK AT TRANSMISSION PASS-THROUGH CONNECTOR

SUBJECT: FLUID LEAKS AT TRANSMISSION PASS-THROUGH CONNECTOR (NEW WIRE HARNESS AND SERVICE KIT)

MODELS: 1991-93 C/K, R/V AND P TRUCKS G-VAN AND ISUZU (EQUIPPED WITH HYDRA-MATIC 4L80-E/4L80-EHD TRANSMISSION)

CONDITION:

SOME VEHICLES MAY EXHIBIT A FLUID LEAK OUT THE TRANSMISSION PASS-THROUGH CONNECTOR CAUSING MATERIAL DEGRADATION ON VEHICLE SIDE CONNECTOR AND WIRING WHICH MAY LEAD TO ERRATIC TRANSMISSION OPERATION.

CAUSE:

"WICKING" OF FLUID BETWEEN WIRE AND INSULATION THROUGH THE PINS AND INTO THE CONNECTOR INTERFACE AND ULTIMATELY TO THE VEHICLE SIDE WIRING.

CORRECTION: (FIGURE 2)

REPLACE THE WIRE HARNESS ASSEMBLY PER YOUR TRANSMISSION SERVICE MANUAL AND INSTALL THIS SERVICE PACKAGE PER INSTRUCTION SHEETS.

DATE OF PRODUCTION: (FIGURE 1)

STARTING MAY 5, 1993 (JULIAN DATE 125), ALL 1993 HYDRA-MATIC 4L80-E/4L80-EHD MODELS WILL HAVE THE NEW WIRING HARNESS.

SERVICE PROCEDURE: (FIGURE 3)

REFER TO THE APPROPRIATE SERVICE MANUAL SECTION FOR PROPER REPLACEMENT PROCEDURES FOR THE TRANSMISSION WIRING HARNESS.

WHEN INSTALLING A S.R.T.A. UNIT OR REPLACING A WIRING HARNESS ON AN ASSEMBLY BUILT PRIOR TO MAY 5, 1993 (JULIAN DATE 125), IT WILL BE NECESSARY TO INSTALL THE SERVICE JUMPER HARNESS INCLUDED IN THE SERVICE PACKAGE. INSTALLATION INSTRUCTIONS ARE INCLUDED IN THIS BULLETIN AND IN THE SERVICE PACKAGE.

WARRANTY INFORMATION:

FOR VEHICLES REPAIRED UNDER WARRANTY, USE:

LABOR OP. DESCRIPTION LABOR TIME

K6554 WIRING HARNESS USE PUBLISHED ASSEMBLY REPLACE LABOR OPERATION TIME

K7000 TRANSMISSION ASSEMBLY USE PUBLISHED REPLACE LABOR OPERATION TIME

ADD: TO SPLICE PASS-THROUGH 0.7 CONNECTOR TO VEHICLE

SERVICE PARTS INFORMATION:

PART NUMBER NAME

24200161 *HARNESS PKG.--AUTOMATIC TRANSMISSION WIRING HARNESS ASM. VEHICLE SIDE HARNESS CONNECTOR ASSEMBLY INSTRUCTION SHEETS MISC. ACCESSORIES

PARTS ARE CURRENTLY AVAILABLE FROM GMSPO.

INSTRUCTIONS:

WIRING HARNESS ASSEMBLY

THE ELECTRICAL WIRING HARNESS IS UPDATED WITH AN EXTRA LENGTH ON ONE OF THE CONDUITS LEADING TO THE PRESSURE CONTROL SOLENOID ON THE CONTROL VALVE ASSEMBLY.

WHENEVER SERVICING A 4L80-E/4L80-EHD TRANSMISSION PRIOR TO 1994 MODEL YEAR AND THE ELECTRICAL WIRING HARNESS IS BEING INSTALLED, THE EXTRA SLACK IN WIRE LENGTH FOR THE PRESSURE CONTROL SOLENOID (PCS) CAN BE TAKEN UP BY TWISTING THE CONDUIT ONE TO TWO TURNS WITH THE CONDUIT THAT LEADS TO THE PULSE WIDTH MODULATED (PWM) SOLENOID, THEN THE PWM AND THE PCS CONDUITS CAN BE CONNECTED. THE TWISTED WIRES WILL TAKE UP THE EXTRA SLACK AND WILL PREVENT ANY LOOSE WIRE FROM BECOMING PINCHED OR CRUSHED WHEN THE OIL PAN IS INSTALLED.

FIGURES: 3


Object Number: 80683  Size: FS


Object Number: 81924  Size: FS


Object Number: 83087  Size: FS

GENERAL MOTORS BULLETINS ARE INTENDED FOR USE BY PROFESSIONAL TECHNICIANS, NOT A "DO-IT-YOURSELFER." THEY ARE WRITTEN TO INFORM THOSE TECHNICIANS OF CONDITIONS OCCURRING ON SOME VEHICLES, OR TO PROVIDE INFORMATION THAT COULD ASSIST IN THE PROPER SERVICE OF A VEHICLE. PROPERLY TRAINED TECHNICIANS HAVE THE EQUIPMENT, TOOLS, SAFETY INSTRUCTIONS AND KNOW-HOW TO DO A JOB PROPERLY AND SAFELY. IF A CONDITION IS DESCRIBED, DO NOT ASSUME THE BULLETIN APPLIES TO YOUR VEHICLE, OR THAT YOUR VEHICLE WILL HAVE THAT CONDITION. SEE A GENERAL MOTORS DEALER SERVICING YOUR BRAND OF GENERAL MOTORS VEHICLE FOR INFORMATION ON WHETHER YOUR VEHICLE MAY BENEFIT FROM THE INFORMATION.

COPYRIGHT 1993. GM POWERTRAIN DIVISION. GENERAL MOTORS CORPORATION. ALL RIGHTS RESERVED.