Step | Action | Value(s) | Yes | No |
---|---|---|---|---|
1 | Perform the Charging System Check . Is the generator OK? | -- | ||
2 |
Is the voltage within the specified range? | 13-16 V | ||
3 | Stop the engine. Perform the Battery Electrical Drain/Parasitic Load Test . Is the parasitic load below the specified value? | 22 ma | System OK | |
4 | Determine the source of the excessive parasitic drain and repair as necessary. Is the repair complete? | -- | System OK | -- |
5 | Was the voltage across the battery terminals with the engine running at 2500 RPM too low? | -- | ||
6 |
Is the voltage above the specified value? | 12 V | ||
7 | Check CKT 225 between the generator and the PCM for an Intermittent shorted/grounded condition or a poor connection. Is CKT 225 OK? | -- | ||
8 | Repair CKT 225 as necessary. Is CKT 225 repair complete? | -- | -- | |
9 | Check the Generator 4-way connector for a mis-wired condition in cavity D. This cavity should not be in this vehicle. Has the mis-wired condition been repaired? | -- | -- | |
10 |
Is the voltage above the specified value? | 12 V | ||
11 | Repair CKT 225 for a shorted, grounded, or open condition. Is the CKT 225 repair complete? | -- | -- | |
12 | Repair or replace the PCM. Refer to Powertrain Control Module Replacement . Is the PCM repair complete? | -- | -- | |
13 | Replace the generator. Refer to Generator Replacement . Is the repair complete? | -- | -- | |
14 |
Is the repair complete? | -- | -- | |
15 |
Is the voltage within the specified range? | 13-16 V | System OK |