Step | Action | Value(s) | Yes | No |
---|---|---|---|---|
1 | Did you perform the Starter System Check? | -- | Go to Starting System Check | |
2 |
Is the voltage greater than the specified value? | 9.5 V | ||
3 |
Is the voltage greater than the specified value? | 9.5 V | ||
4 | Test for voltage at the STARTER relay socket cavity 85 to ground. Is the voltage greater than the specified value? | 9.5 V | ||
5 | Test for voltage between the STARTER relay socket cavity 85 and cavity 86. Is the voltage greater than the specified value? | 9.5 V | ||
6 |
Is the voltage greater than the specified value? | 9.5 V | ||
7 | Is the vehicle equipped with a manual transmission? | -- | ||
8 |
Is the voltage greater than the specified value? | 9.5 V | ||
9 |
Does the engine crank? | -- | ||
10 |
Is the voltage greater than the specified value? | 9.5 V | ||
11 |
Does the engine crank? | -- | ||
12 |
Is the voltage greater than the specified value? | 9.5 V | ||
13 | Measure the voltage between the ignition switch C211 connector D5 and ground. Is the voltage greater than the specified value? | 9.5 V | ||
14 |
Does the engine crank? | -- | Go to Starting System Check | |
15 | Replace the starter. Refer to Starter Motor Replacement . Is the repair complete? | -- | Go to Starting System Check | -- |
16 | Repair the open in CKT 19 (RED) between the battery MaxiFuse® B stud and the STARTER relay. Is the repair complete? | -- | Go to Starting System Check | -- |
17 | Repair the open in CKT 6 (PPL) between the STARTER relay and the starter solenoid. Is the repair complete? | -- | Go to Starting System Check | -- |
18 | Repair the open in CKT 350 (BLK) between the STARTER relay and G102. Is the repair complete? | -- | Go to Starting System Check | -- |
19 | Replace the STARTER relay. Is the replacement complete? | -- | Go to Starting System Check | -- |
20 |
Does the engine crank? | -- | Go to Starting System Check | |
21 | Replace the clutch pedal position switch. Is the repair complete? | -- | Go to Starting System Check | -- |
22 | Repair the open in CKT 1035 (PPL) between the clutch pedal position switch and the STARTER relay. Is the repair complete? | -- | Go to Starting System Check | -- |
23 | Replace the PNP switch. Refer to Park/Neutral Position Switch Replacement in Automatic Transmission. Is the replacement complete? | -- | Go to Starting System Check | -- |
24 | Repair the open in CKT 1035 (PPL) between the PNP switch and the STARTER relay. Is the repair complete? | -- | Go to Starting System Check | -- |
25 | Inspect for an open in CKT 5 (YEL) between the ignition switch and the underhood fuse block. Is an open present in CKT 5 (YEL)? | -- | ||
26 | Repair the open in CKT 5 (YEL) between the ignition switch and the underhood fuse block. Is the repair complete? | -- | Go to Starting System Check | -- |
27 | Repair the open in CKT 806 (PPL) between the underhood fuse block and the clutch pedal position switch (M/T) or the PNP switch (A/T). Is the repair complete? | -- | Go to Starting System Check | -- |
28 | Replace the ignition switch. Refer to Ignition Coil and Ignition Coil Module Replacement . Is the repair complete? | -- | Go to Starting System Check | -- |
29 | Repair the open in CKT 740 (ORN) between the ignition switch and the underhood fuse block. Is the repair complete? | -- | Go to Starting System Check | -- |