Step | Action | Value(s) | Yes | No |
---|---|---|---|---|
1 | Did you perform the HVAC Compressor Controls System Check? | -- | Go to Step 2 | |
2 | Inspect the A/C Compressor fuse at the Underhood Fuse/Relay Center. Is the fuse operational? | -- | Go to Step 4 | Go to Step 3 |
3 |
Is the repair complete? | -- | -- | |
4 | Inspect the IGN -E fuse at the Underhood Fuse/Relay Center. Is the fuse operational? | -- | Go to Step 6 | Go to Step 5 |
5 |
Is the repair complete? | -- | -- | |
6 |
Did the test lamp light? | -- | Go to Step 7 | Go to Step 8 |
7 | Connect a DMM J 39200 from CKT 603 (DK GRN/WHT) cavity 30 of the VCM connector C3 to ground Is there continuity? | -- | Go to Step 9 | Go to Step 10 |
8 |
Did the test lamp light? | -- | Go to Step 11 | Go to Step 12 |
9 | Connect a test lampJ 35616-200 from CKT 459 (DK GRN/WHT) cavity 1 of the VCM connector C3 to ground. Did the test lamp light? | -- | Go to Step 13 | Go to Step 14 |
10 |
Is there continuity? | -- | Go to Step 21 | Go to Step 22 |
11 | Use a J 39200 Digital Multimeter (DMM) in order to test the CKT 762 (DK GRN/WHT) for resistance between the A/C high-pressure cut-off switch cavity A and cavity 25 of the VCM connector C3. Does the DMM show continuity? | -- | Go to Step 15 | Go to Step 16 |
12 | Connect a test lamp J 35616-200 from CKT 66 (LT GRN) cavity H of the HVAC control module connector C2 to ground. Did the test lamp light? | -- | Go to Step 17 | Go to Step 18 |
13 |
Did the test lamp light? | -- | Go to Step 19 | Go to Step 27 |
14 |
Did the test lamp light? | -- | Go to Step 20 | Go to Step 28 |
15 | Replace the A/C high-pressure cut-off switch. Is the repair complete? | -- | -- | |
16 | Repair the open in CKT 762 (DK GRN/WHT) between the A/C high pressure cut-off switch and the VCM. Is the repair complete? | -- | -- | |
17 | Repair the open in CKT 66 (LT GRN) between the HVAC control module and the A/C high-pressure cut-off switch. Is the repair complete? | -- | -- | |
18 |
Did the test lamp light? | -- | Go to Step 25 | Go to Step 26 |
19 | Use a J 39200 DMM in order to test for resistance from CKT 850 (BLK) cavity A of the A/C compressor clutch connector to ground. Does the DMM show continuity? | -- | Go to Step 32 | Go to Step 35 |
20 |
Did the test lamp light? | -- | Go to Step 36 | Go to Step 31 |
21 | Use a J 39200 DMM in order to test CKT 603 (DK GRN) for resistance between the switch and cavity 30 of the VCM connector C3. Does the DMM show continuity? | -- | Go to Step 23 | Go to Step 24 |
22 | Repair the open in CKT 850 (BLK) between the A/C low cut-off pressure switch and ground G104. Is the repair complete? | -- | -- | |
23 | Replace the A/C low-pressure cut-off switch. Is the repair complete? | -- | -- | |
24 | Repair the open in CKT 603 (DK GRN) between the A/C low-pressure cut-off switch and the VCM. Is the repair complete? | -- | -- | |
25 | Replace the HVAC control module. Refer to Control Assembly Replacement . Is the repair complete? | -- | -- | |
26 | Repair the open in CKT 141 (BRN) between the instrument panel fuse block and the HVAC control module. Is the repair complete? | -- | -- | |
27 | Connect a test lamp J 35616-200 from the A/C enable relay CKT 1240 (ORN) cavity C6 and ground. Did the test lamp light? | -- | Go to Step 30 | Go to Step 29 |
28 | Repair the open in CKT 639 (PNK) between the A/C enable relay (underhood fuse-relay center) and the ignition-E fuse (underhood fuse-relay center). Is the repair complete? | -- | -- | |
29 | Repair the open in CKT 1240 (ORN) between the A/C enable relay (underhood fuse-relay center) and the A/C compressor fuse (underhood fuse-relay center). Is the repair complete? | -- | -- | |
30 |
Did the test lamp light? | -- | Go to Step 36 | Go to Step 33 |
31 | Repair the open in CKT 459 (DK GRN/WHT) between the A/C enable relay and the VCM. Is the repair complete? | -- | -- | |
32 | Use a J 39200 DMM in order to test for resistance between Pin B and Pin A of the A/C compressor clutch. Is the resistance less than the recommended value? | 10 ohms | Go to Step 34 | |
33 | Repair the open in CKT 59 (DK GRN) between the A/C enable relay and the A/C compressor clutch. Is the repair complete? | -- | -- | |
34 | Replace the A/C compressor clutch. Refer to Compressor Clutch Plate/Hub Assembly Installation (HT6/HD6). Is the repair complete? | -- | -- | |
35 | Repair the open in CKT 850 (BLK) between the A/C compressor clutch and ground G104. Is the repair complete? | -- | -- | |
36 | Replace the A/C Enable Relay. Is the repair complete? | -- | -- |