Removal Procedure
- Remove the air dryer from
the automatic level control air compressor. Refer to
Automatic Level Control Air Dryer Replacement
.
- Remove the wiring terminals B and C (1) from the automatic
level control air compressor electrical connector.
- Remove the automatic level control air compressor head retaining
bolts.
- Remove the automatic level control air compressor head (2) from
the compressor.
- Remove the O-ring (3) from the automatic level control air compressor.
- Remove the automatic level control air compressor head wires from
the conduit and the tie straps.
Installation Procedure
- Route the automatic level
control air compressor head wires through the tie strap and the conduit.
- Install the O-ring (3) to the automatic level control air compressor.
- Install the automatic level control air compressor head (2) to
the compressor.
Notice: Use the correct fastener in the correct location. Replacement fasteners
must be the correct part number for that application. Fasteners requiring
replacement or fasteners requiring the use of thread locking compound or sealant
are identified in the service procedure. Do not use paints, lubricants, or
corrosion inhibitors on fasteners or fastener joint surfaces unless specified.
These coatings affect fastener torque and joint clamping force and may damage
the fastener. Use the correct tightening sequence and specifications when
installing fasteners in order to avoid damage to parts and systems.
- Install the automatic
level control air compressor head retaining bolts.
Tighten
Tighten the automatic level control air compressor head bolts to 6 N·m
(53 lb in).
- Install the wiring to the B and the C (1) terminals on
the automatic level control air compressor electrical connector.
- Install the air dryer to the automatic level control air compressor.
Refer to
Automatic Level Control Air Dryer Replacement
.