Step | Action | Value(s) | Yes | No |
---|---|---|---|---|
1 | Did you perform the ALC Suspension System Check? | -- | Go to Step 2 | |
2 |
Does the load leveling pump stop running? | -- | Go to Step 3 | Go to Step 8 |
3 | Test CKT 1250 (BLK) at terminal F, of the load leveling timer relay for a short to ground. Is a short to ground present in CKT 1250 (BLK)? | -- | Go to Step 4 | Go to Step 7 |
4 |
Is a short to ground present in CKT 1250 (BLK)? | -- | Go to Step 5 | Go to Step 6 |
5 | Repair the short to ground in CKT 1250 (BLK). Is the repair complete? | -- | -- | |
6 | Replace the load leveling air inflator switch. Refer to Automatic Level Control Inflator Air Switch Replacement . Is the replacement complete? | -- | -- | |
7 | Replace the load leveling timer relay. Refer to Automatic Level Control Relay Replacement . Is the replacement complete? | -- | -- | |
8 | Disconnect the load leveling height sensor. Does the load leveling pump stop running? | -- | Go to Step 9 | Go to Step 10 |
9 | Replace the load leveling height sensor. Refer to Automatic Level Control Sensor and Bracket Replacement . Is the replacement complete? | -- | -- | |
10 |
Is a short to ground present in CKT 321 (YEL) | -- | Go to Step 11 | Go to Step 12 |
11 | Repair the short to ground in CKT 321 (YEL). Is the repair complete? | -- | -- | |
12 |
Does the load leveling pump run? | -- | Go to Step 13 | Go to Step 14 |
13 | Repair the short to voltage on the BLK/LT GRN wire. Is the repair complete? | -- | -- | |
14 | Replace the relay in the load leveling pump. Refer to Air Compressor Relay Replacement . Is the replacement complete? | -- | -- |