- Install the transmission oil cooler lines to the vehicle.
Important:
• | Do not reuse any of the existing oil lines or oil line fittings
if there is excessive corrosion. |
• | Do not reuse any of the existing retaining rings that were removed
from the existing quick connect fittings. All retaining rings being installed
must be new. |
• | Ensure the following procedures are performed when installing
the new retaining rings onto the fittings. |
- Install a new retaining ring (E-clip) into the quick connect fitting
using the following procedure:
- Hook one of the open ends
of the retaining ring in one of the slots in the quick connect fitting.
- Rotate the retaining ring
around the fitting until the retaining ring is positioned with all three ears
through the three slots on the fitting.
- Do not install the new
retaining ring onto the fitting by pushing the retaining ring.
- Ensure that the three
retaining ring ears are seen from inside the fitting and that the retaining
ring moves freely in the fitting slots.
- Install the new retaining ring (E-clip) into the remaining quick
connect fittings.
Notice: Ensure that the cooler line being installed has a plastic cap on each
end that connects to a quick connect fitting. If no plastic cap exists, or
the plastic cap is damaged, obtain a new plastic cap and position on to the
cooler line prior to the cooler line installation.
- Install the cooler lines
to the vehicle.
- Install the cooler line
into the quick connect fitting.
- Insert the cooler line end into the quick connect fitting until
a click is either heard or felt.
- Do not use the plastic
cap on the cooler line in order to install the cooler line into the fitting.
- Pull back sharply on the cooler line in order to ensure that the
cooler line is fastened into the quick connect fitting.
- Position (snap) the plastic
cap onto the fitting. Do not manually depress the retaining ring when installing
the plastic cap onto the quick connect fitting.
- Ensure that the plastic cap is fully seated against the fitting.
- Ensure that no gap is
present between the cap and the fitting.
- Ensure that the yellow
identification band on the tube is hidden within the quick connect fitting.
- A hidden yellow identification
band indicates proper joint seating.
- Install all remaining cooling line ends to the remaining fittings.
- Install the transfer case vent hose, if equipped.
- Raise the transmission
into position.
- Install the exhaust crossover pipe and the transmission support
assembly. Refer to
Transmission Support Replacement
in Frame and Underbody.
- Remove the transmission jack.
Notice: Use the correct fastener in the correct location. Replacement fasteners
must be the correct part number for that application. Fasteners requiring
replacement or fasteners requiring the use of thread locking compound or sealant
are identified in the service procedure. Do not use paints, lubricants, or
corrosion inhibitors on fasteners or fastener joint surfaces unless specified.
These coatings affect fastener torque and joint clamping force and may damage
the fastener. Use the correct tightening sequence and specifications when
installing fasteners in order to avoid damage to parts and systems.
- For vehicles equipped
with a 4.3L engine, install the stud and clip securing the cooler line to
the engine.
Tighten
Tighten the stud to 11 N·m (97 lb in).
- For vehicles equipped
with a 2.2L engine, Install the nut securing the oil cooler lines to the
engine.
Tighten
Tighten the nut to 11 N·m (97 lb in).
- Lower the vehicle.
- Fill the transmission to the proper level with DEXRON® III
transmission fluid. Refer to
Transmission Fluid Check
.