Notice: Refer to Fastener Notice in the Preface section.
- If necessary, perform the following:
1.1. | Install NEW seals to the thermostats. |
1.2. | Install the thermostats. |
1.3. | Install the thermostat cover and bolts. |
Tighten
Tighten the bolts to 21 N·m (15 lb ft).
1.4. | Install a NEW O-ring seal to the thermostat bypass pipe. |
1.5. | Install the thermostat bypass pipe to the thermostat housing. |
- Install a NEW thermostat bypass pipe to water pump O-ring seal.
- Install the thermostat housing crossover using NEW gaskets.
- Install the thermostat housing crossover bolts and nuts.
Tighten
Tighten the bolts/nuts to 21 N·m (15 lb ft).
- Install the water pump inlet pipe bolts.
Tighten
Tighten the bolts to 21 N·m (15 lb ft).
- Install the cooling fan pulley. Refer to
Cooling Fan Pulley Replacement
.
- Install the fuel line bracket bolt at the thermostat housing crossover.
Tighten
Tighten the bolt to 21 N·m (15 lb ft).
- Install the turbocharger coolant return pipe hose.
- Position the turbocharger coolant return pipe hose clamp.
- Install the EGR coolant pipe with O-ring seal to the crossover.
- Install the EGR coolant pipe bolt.
Tighten
Tighten the bolt to 25 N·m (18 lb ft).
- Position the EGR hose clamp at the EGR coolant pipe.
- Install the water outlet. Refer to
Water Outlet Tube Replacement
.
- Install the front oil fill tube. Refer to
Oil Filler Tube Replacement
for the 6.6L (LLY) engine.
- Position the generator bracket.
- Install the generator bracket bolts.
Tighten
Tighten the bolt to 50 N·m (37 lb ft).
- Install the ribbed idler pulley.
Tighten
Tighten the bolt to 43 N·m (32 lb ft).
- Install the heater outlet hose bracket bolt to the generator bracket.
Tighten
Tighten the bolt to 21 N·m (15 lb ft).
- Install the power steering pump bracket to the engine. Refer to
Air Conditioning (A/C) Compressor and Power Steering Pump Bracket Replacement
for the 6.6L (LLY) engine.
- Install the power steering pump. Refer to
Power Steering Pump Replacement
.
- Install the positive cable to the generator.
- Install the generator positive cable to generator nut.
Tighten
Tighten the nut to 9 N·m (80 lb in).
- Connect the ECT sensor electrical connector.
- Connect the generator electrical connector.
- Position the A/C compressor (3), with the hoses attached.
- Install the A/C compressor bolts (1).
Tighten
Tighten the bolts to 50 N·m (37 lb ft).
- Connect the A/C cut out switch electrical connector.
- Connect the A/C compressor clutch electrical connector.
- Position the engine wiring harness to the retainer and secure the retainer.
- Install the engine wiring harness brackets and clamps to the thermostat housing and the air intake pipe with nut and bolt.
Tighten
Tighten the nut and bolt to 25 N·m (18 lb ft).
- Install the drive belt. Refer to
Drive Belt Replacement
for the 6.6L (LLY) engine.
- Install the upper fan shroud. Refer to
Fan Shroud Replacement
.
- Connect the negative battery cables. Refer to
Battery Negative Cable Disconnection and Connection
.
- Install the air cleaner. Refer to
Air Cleaner Replacement
for the 6.6L (LLY) engine.
- Fill the cooling system. Refer to
Cooling System Draining and Filling
.