Generator Replacement 4.8L, 5.3L, and 6.0L Engines
Removal Procedure
- Disconnect the negative battery cable.
Refer to
Battery Negative Cable Disconnection and Connection
.
- Remove the accessory drive belt. Refer to
Drive Belt Replacement - Accessory
in Engine Mechanical - 4.8L, 5.3L,
and 6.0L.
- If necessary, remove the engine sight shield. Refer to
Upper Intake Manifold Sight Shield Replacement
in Engine Mechanical - 4.8L, 5.3L, and
6.0L.
- Disconnect the generator electrical connector (3).
- Remove
the generator cable from the generator, perform the following:
5.1. | Slide the boot down revealing the terminal stud. |
5.2. | Remove the generator cable nut from the terminal stud. |
5.3. | Remove the generator cable. |
- Remove
the generator bolts.
- Remove the generator.
Installation Procedure
- Install
the generator.
Notice: Use the correct fastener in the correct location. Replacement fasteners
must be the correct part number for that application. Fasteners requiring
replacement or fasteners requiring the use of thread locking compound or sealant
are identified in the service procedure. Do not use paints, lubricants, or
corrosion inhibitors on fasteners or fastener joint surfaces unless specified.
These coatings affect fastener torque and joint clamping force and may damage
the fastener. Use the correct tightening sequence and specifications when
installing fasteners in order to avoid damage to parts and systems.
- Install the generator bolts.
Tighten
Tighten the bolts to 50 N·m (37 lb ft).
- Install
the generator cable to the generator, perform the following:
3.1. | Install the generator cable. |
3.2. | Install the generator cable nut to the terminal stud. |
Tighten
Tighten the nut to 9 N·m (80 lb in).
3.3. | Slide the boot over the terminal stud. |
- Connect the generator electrical connector
(3).
- If necessary, install the engine sight shield. Refer to
Upper Intake Manifold Sight Shield Replacement
in Engine Mechanical - 4.8L, 5.3L,
and 6.0L.
- Install the accessory drive belt. Refer to
Drive Belt Replacement - Accessory
in Engine Mechanical - 4.8L, 5.3L,
and 6.0L.
- Connect the negative battery cable. Refer to
Battery Negative Cable Disconnection and Connection
.
Generator Replacement 8.1L Engine
Removal Procedure
- Disconnect the negative battery cable.
Refer to
Battery Negative Cable Disconnection and Connection
.
- Remove the drive belt. Refer to
Drive Belt Replacement - Accessory
in Engine Mechanical - 8.1 L.
- Disconnect the generator electrical connector (1).
- Remove
the generator cable from the generator, perform the following:
• | Slide the boot down revealing the terminal stud. |
• | Remove the generator cable nut from the terminal. |
• | Remove the generator cable. |
- Remove the generator bolts.
- Remove the generator.
Installation Procedure
- Install the generator.
Notice: Use the correct fastener in the correct location. Replacement fasteners
must be the correct part number for that application. Fasteners requiring
replacement or fasteners requiring the use of thread locking compound or sealant
are identified in the service procedure. Do not use paints, lubricants, or
corrosion inhibitors on fasteners or fastener joint surfaces unless specified.
These coatings affect fastener torque and joint clamping force and may damage
the fastener. Use the correct tightening sequence and specifications when
installing fasteners in order to avoid damage to parts and systems.
- Install the generator bolts.
Tighten
Tighten the bolts to 50 N·m (37 lb ft).
- Install
the generator cable to the generator, perform the following:
3.1. | Install the generator cable. |
3.2. | Install the generator cable nut to the terminal. |
Tighten
Tighten the nut to 9 N·m (80 lb in).
3.3. | Slide the boot over the terminal stud. |
- Connect the generator electrical connector
(1).
- Install the drive belt. Refer to
Drive Belt Replacement - Accessory
in Engine Mechanical - 8.1 L.
- Connect the negative battery cable. Refer to
Battery Negative Cable Disconnection and Connection
.