Removal Procedure
Tools Required
• | J 8092 Universal Driver Handle - 3/4 in - 10 |
• | J 23907 Slide Hammer with Bearing
Adapter |
• | J 29369-2 Bushing and Bearing Remover
2-3 in |
- Remove the reaction carrier shaft/internal gear retainer
(668) and the reaction carrier shaft (666) from the input internal gear (664).
- Inspect the reaction carrier shaft (666) and the input internal gear (664)
for the following defects:
• | Damaged or worn bushings |
- Using
J 29369-2 with
J 23907 , remove the reaction carrier shaft front
bushing (665).
- Using
J 25019-14 with
J 7004-A , remove the reaction carrier shaft rear bushing
(667).
Installation Procedure
- Using J 34196-3 which is part of kit
J 34196-B J 34196-B with
J 8092
, install a new reaction carrier shaft front bushing (665).
- Using J 34196-3 which is part of kit
J 34196-B with
J 8092
, install a reaction carrier shaft rear bushing (667).