Inspect the resistance of each shift solenoid between the terminal and the ground.
Important: The resistance of the solenoid can become
infinity ohm when the resistance measurement is made at high temperatures.
If the resistance value is not between the minimum and maximum resistance plot
lines, then measure the solenoid resistance at 20°C (68°F).
Test the operation of the shift solenoid. The shift solenoid is a normally open
solenoid. Air will only pass through the solenoid when it is not energized.
Apply compressed air to the solenoid inlet.
If the solenoid does not allow air to pass thought the solenoid, replace
the solenoid.
Apply B+ and Ground to the solenoid.
If the solenoid allows air to pass through the solenoid, then replace
the solenoid (1).
Test the operation of the timing solenoid. The timing solenoid is a normally
closed solenoid (2). Air will only pass through the solenoid when the solenoid
is energized.
Apply compressed air to the solenoid inlet.
If the solenoid allows air to pass through the solenoid, then replace
the solenoid.
Apply B+ and Ground to the solenoid.
If the solenoid does not allow air to pass thought the solenoid, replace
the solenoid.