Step | Action | Value(s) | Yes | No |
---|---|---|---|---|
DEFINITION: This diagnosis checks for electrical failures back to the battery. | ||||
1 |
Did the test lamp light? | -- | Go to Step 9 | Go to Step 2 |
Did the BLU fusible link wiring jacket stretch or break when pulled? | -- | Go to Step 3 | Go to Step 8 | |
Check the RED (2) Battery Lead to the Generator for a short to ground. Was a short to ground identified? | -- | Go to Step 4 | Go to Step 5 | |
Are the repairs complete? | -- | -- | ||
Inspect the Battery and Generator wiring for additions of aftermarket electrical loads. Was an aftermarket electrical load identified? | -- | Go to Step 6 | Go to Step 7 | |
Are the repairs complete? | -- | -- | ||
Replace the BLU fusible link at the Battery. Are the repairs complete? | -- | Go to Step 9 | -- | |
Locate and repair the open circuit in the RED (2) wire between fusible link Splice S119 and the Generator. Are the repairs complete? | -- | -- | ||
Connect an test lamp between the Battery Junction Block studs and ground. Does the test lamp light? | -- | Go to Step 17 | Go to Step 10 | |
Did the BLU fusible link wiring jacket stretch or break when pulled? | -- | Go to Step 11 | Go to Step 11 | |
Check the RED (2) wire to the Battery Junction Block for a short to ground. Was a short to ground identified? | -- | Go to Step 12 | Go to Step 13 | |
Are the repairs complete? | -- | -- | ||
Inspect the Battery Junction Block wiring for additions of aftermarket electrical loads. Was an aftermarket electrical load identified? | -- | Go to Step 14 | Go to Step 15 | |
Are the repairs complete? | -- | -- | ||
Replace the BLU fusible link at the Generator. Are the repairs complete? | -- | -- | ||
Locate and repair the open circuit in the RED (2) wire between fusible link Splice S115 and the Battery Junction Block. Are the repairs complete? | -- | -- | ||
Check that the connections at the Battery Junction Block are clean and tight. Is the check complete? | -- | -- |