Table 1: | Shift Solenoid Valve State and Gear Ratio 4L60-E |
Table 2: | DTC P0753 1-2 Shift Solenoid Valve (1-2 SS Valve) -- Electrical (2.2L) |
The 1-2 Shift Solenoid Valve (1-2 SS Valve) controls the fluid flow acting on the 1-2 and 3-4 shift valves. The 1-2 SS Valve is a normally-open exhaust valve that is used with the 2-3 Shift Solenoid Valve in order to allow four different shifting combinations. The solenoid attaches to the control valve body within the transmission. The 1-2 SS Valve receives ignition voltage through circuit 1020. The PCM controls the solenoid by providing the ground path on circuit 1222.
When the PCM detects a continuous open or short to ground in the 1-2 SS Valve circuit or the 1-2 SS Valve, then DTC P0753 sets. DTC P0753 is a type A DTC.
• | The system voltage is 10-16 volts. |
• | The engine speed is greater than 450 RPM for 8 seconds. |
• | Not in fuel cutoff. |
• | All of the above conditions are met for 5 seconds and either of the following fail conditions occurs for 5 seconds: |
- | The PCM commands the solenoid ON and the voltage remains high (B+). |
- | The PCM commands the solenoid OFF and the voltage remains low (0 volts). |
• | The PCM commands D2 line pressure. |
• | The PCM inhibits 3-2 downshifts if the vehicle speed is greater than 48 km/h (30 mph). |
• | The PCM freezes shifts adapts from being updated. |
• | The PCM illuminates the Malfunction Indicator Lamp (MIL). |
• | The PCM turns OFF the MIL after three consecutive ignition cycles without a failure reported. |
• | A scan tool can clear the DTC from the PCM history. The PCM clears the DTC from the PCM history if the vehicle completes 40 warm-up cycles without a failure reported. |
• | The PCM cancels the DTC default actions when the fault no longer exists and the ignition is OFF long enough in order to power down the PCM. |
• | Inspect the wiring for poor electrical connections at the PCM. Inspect the wiring for poor electrical connections at the transmission 20-way connector. Look for the following conditions: |
- | A bent terminal |
- | A backed out terminal |
- | A damaged terminal |
- | Poor terminal tension |
- | A chafed wire |
- | A broken wire inside the insulation |
• | When diagnosing for an intermittent short or open condition, massage the wiring harness while watching the test equipment for a change. |
• | An open ignition feed circuit can cause multiple DTCs to set. |
• | A faulty ignition switch may set this code. |
Gear | 1-2 Shift Solenoid | 2-3 Shift Solenoid | Gear Ratio |
---|---|---|---|
1 | ON | ON | 3.059:1 |
2 | OFF | ON | 1.625:1 |
3 | OFF | OFF | 1.000:1 |
4 | ON | OFF | 0.696:1 |
The numbers below refer to the step numbers on the diagnostic table.
This step tests the function of the 1-2 SS Valve and the Automatic Transmission Wiring Harness Assembly.
This step tests for power to the 1-2 SS Valve from the ignition through the fuse.
This step tests the ability of the PCM and the wiring to control the ground circuit.
This step measures the resistance of the Automatic Transmission Wiring Harness Assembly and the 1-2 SS Valve.
Step | Action | Value(s) | Yes | No | ||||||
---|---|---|---|---|---|---|---|---|---|---|
1 | Was the Powertrain On-Board Diagnostic (OBD) System Check performed? | -- | Go to OBD System Check | |||||||
2 |
Important: Before clearing the DTCs, use the scan tool in order to record the Freeze Frame and Failure Records for reference. The Clear Info function will erase the data. Are DTCs P0758, P1860, P0740, and P0785 also set? | -- | ||||||||
3 |
Refer to Electrical Diagnosis, Section 8A. Did you find and correct a problem? | -- | -- | |||||||
Command the 1-2 SS Valve ON and OFF three times while listening to the bottom of the transmission pan (a stethoscope may be necessary). Does the solenoid click when commanded? | -- | Go to Diagnostic Aids | ||||||||
Is the test lamp ON? | -- | |||||||||
Is the test lamp ON when the 1-2 SS Valve is commanded ON, and OFF when commanded OFF? | -- | |||||||||
7 | Repair the open or short to ground in ignition feed circuit 1020 to the 1-2 SS Valve. Refer to Electrical Diagnosis, Section 8A. Did you find and correct a problem? | -- | -- | |||||||
8 | Monitor the test lamp status. Was the test lamp OFF at all times? | -- | ||||||||
9 | Inspect circuit 1222 for an open. Repair the circuit if necessary. Refer to Electrical Diagnosis, Section 8A. Did you find a problem? | -- | ||||||||
10 | Was the test lamp ON at all times? | -- | -- | |||||||
11 | Inspect circuit 1222 for a short to ground. Repair the circuit if necessary. Refer to Electrical Diagnosis, Section 8A. Did you find a problem? | -- | ||||||||
12 | Replace the PCM. Refer to PCM Replacement, Section 6. Is the replacement complete? | -- | -- | |||||||
Is the resistance within the range indicated? | 19-31 ohms | |||||||||
14 |
Is the resistance within the range indicated? | 19-31 ohms | ||||||||
15 | Using J 39200 DVOM, measure the resistance between terminals A and E and ground. Are both readings greater than the specified value? | 250 K ohms | Go to Diagnostic Aids | |||||||
16 |
Are both readings greater than the specified value? | 250 K ohms | ||||||||
17 | Replace the Automatic Transmission Wiring Harness Assembly. Refer to 4L60-E Automatic Transmission On-Vehicle Service. Is the replacement complete? | -- | -- | |||||||
18 | Replace the 1-2 SS Valve. Refer to 1-2 Shift Solenoid Valve Replacement/4L60-E Automatic Transmission On-Vehicle Service. Is the replacement complete? | -- | -- | |||||||
19 | In order to verify your repair, perform the following procedure:
Has the test run and passed? | -- | System OK |
Table 1: | Shift Solenoid Valve State and Gear Ratio 4L60-E |
Table 2: | DTC P0753 1-2 Shift Solenoid Valve (1-2 SS Valve) -- Electrical (4.3L) |
The 1-2 Shift Solenoid Valve (1-2 SS Valve) controls the fluid flow acting on the 1-2 and 3-4 shift valves. The solenoid is a normally-open exhaust valve. With the 2-3 Shift Solenoid Valve (2-3 SS Valve), the 1-2 SS Valve allows four different shifting combinations. The solenoid attaches to the control valve body within the transmission. The 1-2 SS Valve receives ignition voltage through circuit 1020. The VCM controls the solenoid by providing the ground path on circuit 1222.
When the VCM detects a continuous open or short to ground in the 1-2 SS Valve circuit or the 1-2 SS Valve, then DTC P0753 sets. DTC P0753 is a type A DTC.
• | The system voltage is 10-19 volts. |
• | The engine speed is greater than 450 RPM for 8 seconds. |
• | Not in fuel cutoff. |
• | All of the above conditions are met for 5 seconds and either of the following fail conditions occurs for 5 seconds: |
- | The VCM commands the solenoid ON and the voltage remains high (B+). |
- | The VCM commands the solenoid OFF and the voltage remains low (0 volts). |
• | The VCM commands D2 line pressure. |
• | The VCM freezes shift adapts from being updated. |
• | The VCM illuminates the Malfunction Indicator Lamp (MIL). |
• | The VCM turns OFF the MIL after three consecutive ignition cycles without a failure reported. |
• | A scan tool can clear the DTC from the VCM history. The VCM clears the DTC from the VCM history if the vehicle completes 40 warm-up cycles without a failure reported. |
• | The VCM cancels the DTC default actions when the fault no longer exists and the ignition is OFF long enough in order to power down the VCM. |
• | Inspect the wiring for poor electrical connections at the VCM. Inspect the wiring for poor electrical connections at the transmission 20-way connector. Look for the following conditions: |
- | A bent terminal |
- | A backed out terminal |
- | A damaged terminal |
- | Poor terminal tension |
- | A chafed wire |
- | A broken wire inside the insulation |
• | When diagnosing for an intermittent short or open condition, massage the wiring harness while watching the test equipment for a change. |
• | An open ignition feed circuit can cause multiple DTCs to set. |
Gear | 1-2 Shift Solenoid | 2-3 Shift Solenoid | Gear Ratio |
---|---|---|---|
1 | ON | ON | 3.059:1 |
2 | OFF | ON | 1.625:1 |
3 | OFF | OFF | 1.000:1 |
4 | ON | OFF | 0.696:1 |
The numbers below refer to the step numbers on the diagnostic table.
This step tests the function of the 1-2 SS Valve and the Automatic Transmission Wiring Harness Assembly.
This step tests for power to the 1-2 SS Valve from the ignition through the fuse.
This step tests the ability of the VCM and the wiring to control the ground circuit.
This step measures the resistance of the Automatic Transmission Wiring Harness Assembly and the 1-2 SS Valve.
Step | Action | Value(s) | Yes | No | ||||||
---|---|---|---|---|---|---|---|---|---|---|
1 | Was the Powertrain On-Board Diagnostic (OBD) System Check performed? | -- | Go to OBD System Check | |||||||
2 |
Important: Before clearing the DTCs, use the scan tool in order to record the Freeze Frame and Failure Records for reference. The Clear Info function will erase the data. Were DTCs , P0758, P1860, P0740, and P0785 also set? | -- | ||||||||
3 |
Refer to Electrical Diagnosis, Section 8A. Did you find and correct a problem? | -- | -- | |||||||
Command the 1-2 SS Valve ON and OFF three times while listening to the bottom of the transmission pan (a stethoscope may be necessary). Did the solenoid click when commanded? | -- | Go to Diagnostic Aids | ||||||||
Is the test lamp ON? | -- | |||||||||
6 | Repair the open or short to ground in ignition feed circuit 1020 to the 1-2 SS Valve. Refer to Electrical Diagnosis, Section 8A. Did you find and correct a problem? | -- | -- | |||||||
Install a test lamp between cavity E and cavity A of the J 39775 Jumper Harness. Using the transmission output control function, command the 1-2 SS Valve ON and OFF three times. Does the test lamp illuminate when you command the shift solenoid ON and turn off when you command OFF? | 5ohms | |||||||||
8 | Inspect circuit 1222 for an open or a short to ground. Repair the circuit if necessary. Refer to Electrical Diagnosis, Section 8A. Did you find a problem? | -- | ||||||||
9 | Replace the VCM. Refer to VCM Replacement, Section 6. Is the replacement complete? | -- | -- | |||||||
Is the resistance within the specified range? | 19-31 ohms | |||||||||
11 |
Is the resistance within the specified range? | 19-31 ohms | ||||||||
12 | Measure the resistance between terminals A and E and ground. Are both readings greater than the specified value? | 250 K ohms | Go to Diagnostic Aids | |||||||
13 |
Are both readings greater than the specified value? | 250 K ohms | ||||||||
14 | Replace the Automatic Transmission Wiring Harness Assembly. Refer to 4L60-E Automatic Transmission On-Vehicle Service. Is the replacement complete? | -- | -- | |||||||
15 | Replace the 1-2 SS Valve. Refer to 1-2 Shift Solenoid Valve Replacement/4L60-E Automatic Transmission On-Vehicle Service. Is the replacement complete? | -- | -- | |||||||
16 | In order to verify your repair, perform the following procedure:
Has the test run and passed? | -- | System OK |