Step | Action | Value(s) | Yes | No |
---|---|---|---|---|
SCHEMATIC REFERENCE: Headlights Schematics | ||||
1 | Did you perform the Lighting System Diagnostic System Check? | -- | Go to Step 2 | |
2 | Did the high beam headlamps operate properly? | -- | Go to Step 3 | |
3 | Inspect for poor connections at the instrument panel cluster (IPC). Refer to Testing for Intermittent Conditions and Poor Connections and Connector Repairs in Wiring Systems. Did you find and correct the condition? | -- | Go to Step 5 | Go to Step 4 |
4 | Replace the IPC. Refer to Instrument Cluster Replacement in Instrument Panel, Gauges and Console. Did you complete the repair? | -- | Go to Step 5 | -- |
5 | Operate the system in order to verify the repair. Did you find and correct the condition? | -- | System OK | Go to Step 2 |