Removal Procedure
Important: The quarter panel is attached to the vehicle structure with spot-welds, except
at the rear roof pillar where it is silicon-bronze welded (1) to the door frame
opening outer panel. Due to the manner in which the quarter panel attached to the
door frame, a special sectioning procedure has been developed for improved serviceability.
- Remove all related panels and components including stationary glass.
Important: When replacing panels that involve servicing stationary glass, refer to GM
Service Bulletin No. 43-10-48 before performing any priming or refinishing
work.
- Visually inspect and restore as much of the damage as possible to factory
specifications.
- Remove sealers and anti-corrosion materials as necessary.
- Note the size of the service part and locate
the sectioning joints at the sail panels (2) and rocker panel accordingly.
- Measure 50 mm (2 in) down (3) from the factory silicon-bronze
joint (1) to locate sectioning cut.
- Locate, mark, and drill out all factory welds. Note the number and location
of welds for installation of the service assembly.
- Remove the damaged quarter panel.
Installation Procedure
- Prepare the mating surfaces as necessary.
- Temporarily position the service panel on the vehicle.
- Trim the original panel to leave a gap of one
and one-half times the thickness of the metal at the sectioning joint location.
- Cut a 100 mm (4 in) piece from the original quarter panel
for backing plates (2).
- Remove the flange on each side of the backing plates so that they will
fit beyond the sectioning joints.
- Drill 8 mm (5/16 in) plug weld holes as necessary in the
locations noted from the original panel.
- Drill plug weld holes along the sectioning cuts of the service part.
These should be located approximately 25 mm (1 in) from the edge of
the cuts.
- Prepare the mating surfaces and position the backing plates with 50 mm
(2 in) of the backing plates.
- Check for proper fit and alignment.
- Plug weld accordingly.
- Stitch weld along the entire joints.
- Make 25 mm (1 in) gaps between them.
- Go back and complete the stitch weld. This will create solid joints with
minimal heat distortion.
- Complete all other welds and sectioning procedures as necessary.
Important: Do not combine paint systems. Refer to paint manufacturers recommendations.
- Prime with 2-part catalyzed primer.
- Apply sealers and anti-corrosion materials as necessary.
- Install all related panels and components.