Instrument Cluster Replacement Chevrolet

Removal Procedure


    Object Number: 288305  Size: SH
  1. Remove the instrument panel (IP) accessory trim plate. Refer to Instrument Panel Accessory Trim Plate Replacement .
  2. Remove the screws (6) from the top of the IP cluster (5).
  3. Remove the IP cluster (5) pulling rearward.
  4. Disconnect the electrical connector (1) from the IP cluster (5).
  5. Remove the IP cluster (5) from IP (3).

Installation Procedure


    Object Number: 288305  Size: SH
  1. Connect the electrical connector (1) to the IP cluster (5).
  2. Position the IP cluster retainer tabs (4) into the IP (3).
  3. Install the instrument panel cluster (5) to the IP (3).
  4. Notice: Use the correct fastener in the correct location. Replacement fasteners must be the correct part number for that application. Fasteners requiring replacement or fasteners requiring the use of thread locking compound or sealant are identified in the service procedure. Do not use paints, lubricants, or corrosion inhibitors on fasteners or fastener joint surfaces unless specified. These coatings affect fastener torque and joint clamping force and may damage the fastener. Use the correct tightening sequence and specifications when installing fasteners in order to avoid damage to parts and systems.

  5. Install the IP cluster screws (6).
  6. Tighten
    Tighten the screws to 2 N·m (18 lb in).

  7. Install the instrument panel accessory trim plate. Refer to Instrument Panel Accessory Trim Plate Replacement .

Instrument Cluster Replacement Pontiac

Removal Procedure


    Object Number: 288303  Size: SH
  1. Remove the instrument panel (IP) trim pad. Refer to Instrument Panel Trim Pad Replacement
  2. Remove the screws (1, 3) from the top of the IP cluster (2).
  3. Remove the IP cluster (2) pulling rearward.
  4. Disconnect the electrical connector (5) from the IP cluster (2).
  5. Remove the IP cluster (2) from IP carrier.

Installation Procedure


    Object Number: 288303  Size: SH
  1. Connect the electrical connector (5) to the IP cluster (2).
  2. Position the IP cluster retainer tabs (4) into the IP carrier.
  3. Install the IP cluster (2) to the IP carrier.
  4. Notice: Use the correct fastener in the correct location. Replacement fasteners must be the correct part number for that application. Fasteners requiring replacement or fasteners requiring the use of thread locking compound or sealant are identified in the service procedure. Do not use paints, lubricants, or corrosion inhibitors on fasteners or fastener joint surfaces unless specified. These coatings affect fastener torque and joint clamping force and may damage the fastener. Use the correct tightening sequence and specifications when installing fasteners in order to avoid damage to parts and systems.

  5. Install the IP cluster screws (1, 3).
  6. Tighten
    Tighten the screws to 2 N·m (18 lb in).