Step | Action | Yes | No |
---|---|---|---|
Schematic Reference: Headlights/Daytime Running Lights (DRL) Schematics | |||
1 | Did you review the Lighting System Description and Operation and perform the necessary inspections? | Go to Step 2 | |
2 | Verify that the daytime running lamps are on with the park brake applied. Does the system operate normally? | Go to Testing for Intermittent Conditions and Poor Connections | Go to Step 3 |
3 |
Is a high resistance condition present? | Go to Step 5 | Go to Step 4 |
4 | Replace the DRL control module. Refer to Daytime Running Lights (DRL) Control Module Replacement . Is the replacement complete? | Go to Step 8 | -- |
5 |
Is an open condition present? | Go to Step 6 | Go to Step 7 |
6 | Locate and repair the open in the DRL relay control circuit between the brake switch connector and the DRL control module. Refer to Wiring Repairs . Is the repair complete? | Go to Step 8 | -- |
7 | Replace the parking brake switch. Refer to Parking Brake Indicator Switch Replacement . Is the replacement complete? | Go to Step 8 | -- |
8 | Operate the system in order to verify the repair. Did you correct the condition? | System OK | Go to Step 3 |