• | J 8001 Dial Indicator Set |
• | J 8087 Cylinder Bore Gage |
• | J 45059 Angle Meter |
• | Wear |
• | Taper |
• | Runout |
• | Ridging |
13.1. | Temporarily install the crankshaft. Measure the crankshaft flange runout. |
13.2. | Hold a gauge plate flat against the crankshaft flange. |
13.3. | Place J 8001 indicator set (dial indicator stem) on the transmission mounting bolt hole boss. Set the indicator to zero. |
13.4. | Record the readings obtained from all of the bolt hole bosses. The measurements should not vary more than 0.25 mm (0.010 in). |
13.5. | Recheck the crankshaft flange runout if the readings vary more than 0.25 mm (0.010 in). If the crankshaft flange runout is within the specification, replace the engine block. |
Caution: Refer to Fastener Caution in the Preface section.
15.1. | Tighten the crankshaft bearing cap bolts to 25 N·m (18 lb ft). |
15.2. | Use J 45059 meter to tighten the crankshaft bearing cap bolts an additional 180 degrees. |
Note: Perform the following inspections, and reconditioning (if necessary), with the crankshaft main bearing caps installed and tightened to specification.