Removal Procedure
- Disconnect the hybrid battery. Refer to
Hybrid Battery Service Disconnect/Connect
.
- Remove the air cleaner outlet duct. Refer to
Air Cleaner Outlet Duct Replacement
.
- Remove the drive belt. Refer to
Drive Belt Replacement
.
- Drain the cooling system. Refer to
Cooling System Draining and Filling
.
- Recover the refrigerant. Refer to
Refrigerant Recovery and Recharging
.
- Unclip the battery positive cable jumper block (1) from the engine control module (ECM) bracket (4).
- Disconnect the ECM electrical connectors (2) and the transmission control module (TCM) electrical connector (3).
- Remove the ECM bracket bolts (1), nuts (2) and ECM bracket (3).
- Remove the generator control module cover bolts (1) and cover (2).
Caution: To help avoid personal injury, additional precautions must be taken prior to working on the generator control module or the generator starter. After removing the 36V battery cables from the generator battery, remove both
engine wiring harness connectors from the generator control module. Wait at least 5 minutes and then remove the generator control module cover. Verify voltage levels at all 36V, 12V, and 3-phase connections, are less than 3 volts using
a DMM before proceeding.
- Check the generator control module for voltage potential, in order to ensure that the module has been disabled.
10.1. | Measure from the 36-volt positive terminal (3) to a known good chassis ground. The voltage should be less than 3 volts. |
10.2. | Measure from the 12-volt positive terminal (4) to a known good chassis ground. The voltage should be less than 3 volts. |
10.3. | Measure from the ground terminal (2) to a known good chassis ground, checking for continuity. |
Caution: To help avoid personal injury, always treat the 3-phase cable and connectors as if voltage is present and as if the surface of all parts
of the cable is hot.
- Verify that the generator control module 3-phase cables are disabled.
11.1. | Measure from each phase 1, 2 and 3 connection (1) to a known good chassis ground. The voltage should be less than 3 volts. |
11.2. | After verifying that there is no voltage present, the generator control module 3-phase cables can now be removed from the generator control module. |
- Remove the battery positive terminal block nuts (1) and reposition the battery positive terminal block (2).
- Remove the 3-phase cable terminal block nuts (3) and reposition the 3-phase cable terminal block (4).
- Remove the bolt securing the 3-phase cables to the oil level indicator bracket.
- Disconnect the upper radiator hose from the cylinder head and secure it out of the way.
- Disconnect the engine wiring harness electrical connectors next to the generator starter and secure them out of the way.
- Remove the upper generator starter bolt (1).
- Raise the vehicle and disconnect the air conditioning (A/C) compressor hose assembly lines from the A/C compressor. Refer to
Compressor Hose Assembly Replacement
.
- Remove the lower generator starter bolts (2).
- Remove the generator starter from the vehicle with the 3-phase cables.
- Remove the generator starter cover bolts (1) and the 3-phase cable bracket bolts (2).
- Remove the 3-phase cable nuts underneath the cover.
- Remove the 3-phase cable bolts (1).
Installation Procedure
Notice: Refer to Fastener Notice in the Preface section.
- Install the 3-phase cable bolts (1) to the generator starter.
Tighten
Tighten the nuts and bolts to 8 N·m (71 lb in).
- Install the 3-phase cable nuts underneath the generator starter cover.
Tighten
Tighten the nuts to 8 N·m (71 lb in).
- Install the generator starter cover bolts (1) and the 3-phase cable bracket bolts (2).
Tighten
Tighten the bolts to 5 N·m (44 lb in).
- Install the generator starter to the vehicle with the 3-phase cables.
- Install the lower generator starter bolts (2).
Tighten
Tighten the bolts to 58 N·m (43 lb ft).
- Install the A/C compressor hose assembly lines to the A/C compressor. Refer to
Compressor Hose Assembly Replacement
.
- Install the upper generator starter bolt (1).
Tighten
Tighten the bolt to 58 N·m (43 lb ft).
- Connect the engine wiring harness electrical connectors next to the generator starter.
- Install the upper radiator hose to the cylinder head.
- Install the bolt securing the 3-phase cables to the oil level indicator bracket.
Tighten
Tighten the bolt to 10 N·m (89 lb in).
- Install the 3-phase cable terminal block (4) and nuts (3).
Tighten
Tighten the bolt to 10 N·m (89 lb in).
- Install the battery positive terminal block (2) and nuts (1).
Tighten
Tighten the bolt to 10 N·m (89 lb in).
- Install the generator control module cover bolts (1) and cover (2).
Tighten
Tighten the bolt to 10 N·m (89 lb in).
- Install the ECM bracket (3), bolts (1) and nuts (2).
Tighten
Tighten the bolt to 10 N·m (89 lb in).
- Connect the ECM electrical connectors (2) and the TCM electrical connectors (3).
- Clip in the battery positive cable jumper block (1) to the ECM bracket (4).
- Recharge the A/C system. Refer to
Refrigerant Recovery and Recharging
.
- Fill the cooling system. Refer to
Cooling System Draining and Filling
.
- Install the drive belt. Refer to
Drive Belt Replacement
.
- Install the air cleaner outlet duct. Refer to
Air Cleaner Outlet Duct Replacement
.
- Connect the hybrid battery. Refer to
Hybrid Battery Service Disconnect/Connect
.
- Using a Tech 2, command an autostart in order to verify that the system is working properly.