Step | Action | Yes | No |
---|---|---|---|
Schematic Reference: Exterior Lights Schematics Connector End View Reference: Master Electrical Component List in Wiring Systems | |||
1 | Did you perform the Lighting System Diagnostic System Check? | Go to Step 2 | |
2 |
Do the park lamps operate properly? | Go to Testing for Intermittent Conditions and Poor Connections in Wiring Systems | Go to Step 3 |
3 |
Does the data parameter display ON? | Go to Step 4 | Go to Step 5 |
4 |
Did all of the park lamps turn ON and OFF? | Go to Step 18 | Go to Step 6 |
5 |
Does the Park Lamp Switch Input data parameter display ON? | Go to Step 16 | Go to Step 14 |
6 |
Does the test lamp illuminate? | Go to Step 7 | Go to Step 12 |
7 | Connect a test lamp between the Park LP relay switch side supply voltage circuit and ground. Does the test lamp illuminate? | Go to Step 8 | Go to Step 21 |
8 |
Did the test lamp turn ON and OFF? | Go to Step 9 | Go to Step 13 |
9 |
Did all of the park lamps illuminate? | Go to Step 17 | Go to Step 10 |
10 |
Does the test lamp illuminate? | Go to Step 19 | Go to Step 11 |
11 | Test the park lamp supply voltage circuit for a high resistance or open. Refer to Circuit Testing and Wiring Repairs in Wiring Systems. Did you find and correct the condition? | Go to Step 26 | Go to Step 20 |
12 | Test the control side supply voltage circuit of the Park LP relay for a high resistance, an open or a short to ground. Refer to Circuit Testing and Wiring Repairs in Wiring Systems. Did you find and correct the condition? | Go to Step 26 | Go to Step 18 |
13 | Test the park lamp relay control circuit of the Park LP relay for a short to battery positive voltage or an open. Refer to Circuit Testing and Wiring Repairs in Wiring Systems. Did you find and correct the condition? | Go to Step 26 | Go to Step 18 |
14 | Test the ground circuit of the headlamp switch for a high resistance or an open. Refer to Circuit Testing and Wiring Repairs in Wiring Systems. Did you find and correct the condition? | Go to Step 26 | Go to Step 15 |
15 | Test the park lamp switch on signal circuit of the headlamp switch for a high resistance or an open. Refer to Circuit Testing and Wiring Repairs in Wiring Systems. Did you find and correct the condition? | Go to Step 26 | Go to Step 18 |
16 | Inspect for poor connections at the harness connector of the headlamp switch. Refer to Testing for Intermittent Conditions and Poor Connections and Connector Repairs in Wiring Systems. Did you find and correct the condition? | Go to Step 26 | Go to Step 22 |
17 | Inspect for poor connections at the Park LP relay. Refer to Testing for Intermittent Conditions and Poor Connections and Connector Repairs in Wiring Systems. Did you find and correct the condition? | Go to Step 26 | Go to Step 23 |
18 | Inspect for poor connections at the harness connector of the DIM. Refer to Testing for Intermittent Conditions and Poor Connections and Connector Repairs in Wiring Systems. Did you find and correct the condition? | Go to Step 26 | Go to Step 24 |
19 | Inspect for poor connections at the inoperative park lamp bulb. Refer to Testing for Intermittent Conditions and Poor Connections and Connector Repairs in Wiring Systems. Did you find and correct the condition? | Go to Step 26 | Go to Step 25 |
20 | Repair the open or high resistance in the park lamp ground circuit. Refer to Circuit Testing and Wiring Repairs in Wiring Systems. Did you complete the repair? | Go to Step 26 | -- |
21 | Repair the high resistance or open in the switch side supply voltage circuit of the Park LP relay. Refer to Circuit Testing and Wiring Repairs in Wiring Systems. Did you complete the repair? | Go to Step 26 | -- |
22 | Replace the headlamp switch. Refer to Headlamp Switch Replacement . Did you complete the replacement? | Go to Step 26 | -- |
23 | Replace the Park LP relay. Refer to Relay Replacement in Wiring Systems. Did you complete the replacement? | Go to Step 26 | -- |
24 |
Important:: After replacement perform the setup procedure for the DIM. Refer to Body Control Module (BCM) Programming/RPO Configuration in Body Control System. Replace the DIM. Refer to Dash Integration Module Replacement in Body Control System. Did you complete the replacement? | Go to Step 26 | -- |
25 | Replace the inoperative park lamp bulb. Did you complete the replacement? | Go to Step 26 | -- |
26 | Operate the system in order to verify the repair. Did you correct the condition? | System OK | Go to Step 2 |