Intake Manifold Replacement - Left Side LLY, LBZ
Removal Procedure
- Remove the center intake manifold. Refer to
Center Intake Manifold Replacement
.
- Remove the auxiliary generator, if equipped. Refer to
Auxiliary Generator Replacement
.
- Remove the left fuel rail. Refer to
Fuel Injection Fuel Rail Assembly Replacement - Bank 2
.
- Remove the injection pump. Refer to
Fuel Injection Pump Replacement
.
- Remove the intake manifold bolts/nuts.
Important: The intake manifold uses sealer. Pry at the area by the fuel rail bolt holes in order to avoid damage to the sealing surface.
- Remove the intake manifold.
- To prevent entry of debris into the cylinder head, tape the openings.
- Clean the gasket surfaces.
Installation Procedure
- Apply a 2-3 mm (1/8 in) wide, by 0.5-1.5 mm (1/16 in) high bead of
sealant to the intake manifold. Refer to
Adhesives, Fluids, Lubricants, and Sealers
.
- Install the intake manifold.
- Install the intake manifold bolts/nuts.
Notice: Refer to Fastener Notice in the Preface section.
- Tighten the intake manifold bolts/nuts.
Tighten
Tighten the bolts/nuts in the sequence shown to 25 N·m (18 lb ft).
- Install the fuel injector pump. Refer to
Fuel Injection Pump Replacement
.
- Install the left fuel rail. Refer to
Fuel Injection Fuel Rail Assembly Replacement - Bank 2
.
- Install the auxiliary generator, if equipped. Refer to
Auxiliary Generator Replacement
.
- Install the center intake manifold. Refer to
Center Intake Manifold Replacement
.
Intake Manifold Replacement - Left Side LMM
Removal Procedure
- Remove the center intake manifold. Refer to
Center Intake Manifold Replacement
.
- Remove the auxiliary generator, if equipped. Refer to
Auxiliary Generator Replacement
.
- Remove the left fuel rail. Refer to
Fuel Injection Fuel Rail Assembly Replacement - Bank 2
.
- Remove the injection pump. Refer to
Fuel Injection Pump Replacement
.
- Remove the intake manifold bolts/nuts.
Important: The intake manifold uses sealer. Pry at the area by the fuel rail bolt holes in order to avoid damage to the sealing surface.
- Remove the intake manifold.
- To prevent entry of debris into the cylinder head, tape the openings.
- Clean the gasket surfaces.
Installation Procedure
- Apply a 2-3 mm (1/8 in) wide, by 0.5-1.5 mm (1/16 in) high bead of
sealant to the intake manifold. Refer to
Adhesives, Fluids, Lubricants, and Sealers
.
- Install the intake manifold.
- Install the intake manifold bolts/nuts.
Notice: Refer to Fastener Notice in the Preface section.
- Tighten the intake manifold bolts/nuts.
Tighten
Tighten the bolts/nuts in the sequence shown to 25 N·m (18 lb ft).
- Install the fuel injector pump. Refer to
Fuel Injection Pump Replacement
.
- Install the left fuel rail. Refer to
Fuel Injection Fuel Rail Assembly Replacement - Bank 2
.
- Install the auxiliary generator, if equipped. Refer to
Auxiliary Generator Replacement
.
- Install the center intake manifold. Refer to
Center Intake Manifold Replacement
.