Step | Action | Value(s) | Yes | No | ||||
---|---|---|---|---|---|---|---|---|
1 | Inspect the ignition (IGN) 1 fuse. Is the ignition (IGN) 1 fuse open? | -- | Go to Step 2 | Go to Step 3 | ||||
2 | Repair the short to ground in CKT 39. Is the repair complete? | -- | Go to Charging System Check | -- | ||||
3 |
Is the voltage equal to the specified value? | 5V | Go to Step 4 | Go to Step 9 | ||||
4 | Measure the voltage from the generator battery (Bat) terminal to ground. Is the voltage equal to the specified value? | 9-14V | Go to Step 5 | Go to Step 12 | ||||
5 |
Is the voltage equal to the specified value? | 13-16V | Go to Step 6 | Go to Step 8 | ||||
6 | Load test the generator. Generator Assembly Check Did the generator test OK? | -- | Go to Step 7 | Go to Step 8 | ||||
7 | Replace the battery. Refer to Battery Replacement. Is the repair complete? | -- | Go to Charging System Check | -- | ||||
8 |
Is the repair complete? | -- | Go to Charging System Check
| -- | ||||
9 | Inspect for a poor connection or an open in CKT 225. Is there a poor connection or an open in CKT 225? | -- | Go to Step 10 | Go to Step 11 | ||||
10 | Repair the poor connection or the open in CKT 225. Is the repair complete? | -- | Go to Charging System Check | -- | ||||
11 | Replace the powertrain control module (PCM). Powertrain Control Module Replacement/Programming Is the repair complete? | -- | Go to Charging System Check | -- | ||||
12 | Repair one of the following conditions:
Is the repair complete? | -- | Go to Charging System Check | -- |